§ 8-4. CHAP to review.
(a) Referral by Building Official.
Within 2 days of receiving a permit application for or involving a regulated alteration, the Building Official must forward the application, together with all accompanying plans and specifications, to the Commission.
(b) Plans, etc., to be available.
(1) On request of the Commission or its staff, the applicant must submit to the Commission any additional plans, elevations, and other related information needed to determine the appropriateness of the proposed regulated alteration.
(2) The Commission may not make any determination concerning the proposed regulated alteration until it is satisfied that:
(i) the permit application is complete; and
(ii) the Commission has received all other needed documents and information, as requested.
(c) CHAP approval prerequisite for permit.
The Building Official may not issue a permit for any regulated alteration unless the Commission first issues an Authorization to Proceed.