§ 22-10. Review and approval of plan.
(a) Review and comment.
(1) The Department must perform a comprehensive review of the plans for each phase of site design to determine compliance with this Division II.
(2) For each plan phase, coordinated comments will be provided that reflect input from all appropriate agencies, including Planning, Zoning, and Public Works.
(3) At each phase of project design, comments from the Department and other appropriate agencies must be addressed by the applicant and approval received before subsequent submissions.
(b) Conditions.
In approving a plan, the Department may impose any conditions that it considers necessary or appropriate to:
(1) ensure compliance with this Division II; and
(2) preserve the public health and safety.
(c) Notification.
After the Department has completed its comprehensive review for each phase of site design, the Department must notify the applicant of:
(1) the Department's approval of the plan;
(2) the Department's disapproval of the plan, together with:
(i) the reasons for disapproval; and
(ii) any modifications that the Department requires for approval; or
(3) if no decision has yet been made:
(i) the status of the review process; and
(ii) the anticipated date of completion.
(d) Endorsement.
A stormwater management plan is not valid until the plan has been endorsed and dated by the Department.